1. Concrete segregation caused by excess water. Concrete segregation caused by imbalanced admixture ratio. Concrete segregation caused by the sand and gravel material itself. The concrete itself does not segregate, but its slump needs to be significantly reduced to adapt to the construction requirements of special circumstances.
2. After adding this product according to the degree of concrete segregation at the construction site, stir quickly for more than 3 minutes to restore the concrete to a construction-ready state. Add 0.5-1kg to 1 cubic meter of concrete. Depending on the slump of the concrete on site, the amount can be fine-tuned. If the slump is small, you can add a little less. If the slump is large, you can add a little more. </p