When using the floor pump lubricating agent, you first need to check for damage, and then flush it. After flushing, proportion it according to the amount of clean water. Since each company's lubricating agent has different proportions of clean water, it is important to check before purchasing. It is recommended to consult or read the dosage stated on the package. One package of our company's lubricating agent is generally between 25-35 kg for ground pumps
The first step
Check whether the delivery pipeline is damaged , leakage. If there is damage or leakage, please repair or replace the pipeline and related parts before proceeding to the next step.
Part 2
Use 100 to 150 kilograms of clean water to flush the pipeline. After flushing the pipeline, the residual clean water in the pipeline must be drained. Do not allow a large amount of residual clean water to remain in the pipeline. In this way It will dilute the viscosity of the lubricant and fail to achieve the best effect of lubricating the lubricant.
The third step
The amount of lubricating agent for the floor pump is twice that of the lubricating agent for the vehicle pump. The dosage should be 25 meters per package of lubricating agent and 50 to 60 kilograms of clean water. For example, (taking a 100-meter pipeline as an example, the amount of lubricant is 4 bags, and the water is 200 to 250 pounds). After cleaning the pipes with clean water, prepare the corresponding clean water according to the length of the pipes. You can directly prepare the pipe lubricant solution in the hopper. When preparing the lubricating agent solution, slowly pour the lubricating water into the water after opening the packaging bag, and stir with a stick while pouring. It is taboo to pour the lubricating agent into the water quickly and stir unevenly.
Step 4
When the concrete tank truck arrives at the construction site and all construction preparations are made, the Kaizheng pump pumps the lubricant solution to lubricate the pipeline. The lubricant solution discharged from the outlet of the conveying pipe is discharged outside the formwork and cannot be poured directly into the building structure. When the lubricating agent solution in the hopper is almost finished pumping, start putting concrete into the hopper and continue pumping without interruption. After the lubricating agent solution and lubricating agent solution at the outlet of the conveying pipe are completely removed and the concrete becomes like the feed port, it can be normal. Poured. After the lubricant solution is discharged, it will evaporate naturally after 72 hours, leaving no residue after evaporation. Because the lubricant is relatively slippery, construction workers should not step on the lubricant solution when walking to prevent slipping. </p